|

 |
Overview of the Trans-Tokyo Bay Highway
The Trans-Tokyo Bay Highway, also known as the Tokyo Wan Aqua-line, is
an approximately 15km highway linking Kawasaki City in Kanagawa Prefecture
on the west side of Tokyo Bay with Kisarazu City in Chiba Prefecture on
the east side of the bay. Construction of the highway is currently proceeding,
and plans call for its completion on December 18, 1997. The Tokyo Wan Aqua-line
will link the Bayside Route of the Tokyo Expressway with the Higashi-Kanto
Highway. When it is completed, the length of a trip between the city halls
of Kawasaki and Kisarazu will be shortened 70km--from 100km to 30km.
The volume of shipping traffic in Tokyo Bay is extremely high. In view
of the need to allow for sufficient shipping lanes and other factors, it
was deemed necessary to construct the first approximately 10km segment of
the Tokyo Wan Aqua-line extending from Kawasaki within an undersea tunnel.
The remaining approximately 5km to Kisarazu is spanned by a bridge. Since
this section of the bay is also traversed by numerous ships, the first 750m
section of the bridge is elevated 27m above the water on 12 towers, allowing
for the passage of 2,000t-class ships.
The Tokyo Wan Aqua-line encompasses two man-made islands--the Kawasaki
Man-Made Island midway along the undersea tunnel and the Kisarazu Man-Made
Island (also known as the Umihotaru, the Japanese name of a luminous, approximately
3mm-long crustacean found locally) where the tunnel joins the bridge. The
Kawasaki Man-Made Island, which has a diameter of approximately 200m, incorporates
ventilation towers. The above-water portion of the Kisarazu Man-Made Island
is 650m long and 100m wide and includes ventilation towers as well as a
parking area.
Kajima is responsible for the western portion of the Kawasaki Man-Made
Island and the Kawajin North region of the tunnel extending from the island
to Kawasaki. Construction of these sections was begun in May 1989. |
|
|
The Kawasaki Man-Made Island
Kawasaki Man-Made Island, which weighs about 650,000t, has a 98m-wide
core. The island is serving as the launching base for shield-driving machines
that are boring four tunnels--the largest undersea holes ever created by
mankind. The two tunnels stretching from the island to Kawasaki are together
referred to as the Kawasaki Tunnel, and the two tunnels extending from the
island toward Kisarazu are together referred to as the Central Tunnel. Located
20m beneath the seabed, which is about 28m below the water's surface, these
tunnels have 14.14m external diameters, making them the world's largest
tunnels created by the shield-tunneling method.
The Kawasaki Man-Made Island was created in the following manner.
„First, a firm foundation extending 32m below the soft seabed of Tokyo Bay
was created through the use of the SCP and DMM methods. In the SCP method,
steel pipes with diameters of approximately 1m were driven into the seabed.
Sand was then injected through the pipes into the seabed under pressure
to form stable, hard-packed sand columns. The DMM method involved the mixing
of a stabilizer material similar to cement with the soft sea bottom material.
The two materials underwent a chemical reaction when combined, thus improving
the stability of the seabed.
„Next, the circumference of the island was encircled with a donut-like struc-ture,
with the inner and outer walls clad in protective steel jackets, and a sand-based
composite soil material was placed in the gap between the two layers, creating
an artificial base for the island's construction.
„After the installation of interior guide walls, electromill excavating
devices were used to dig spaces for the individual elements of an underground
wall, following which a framework of steel reinforcement bars was set up
and concrete pouring commenced. Using Kajima's precision management system
(a weighted plumb-line system) to great advantage, the excavation for each
of the 28 wall elements was performed to a depth of 119m while holding deviation
to within 70mm, thus creating the world's largest cylindrical underground
continuous wall.
„After completing the concrete pouring for the underground wall and water
drainage, the interior guide walls and interior jacket were removed, using
a 4,100t barge-mounted crane to lift each 1,100t jacket block.
„More than 10 backhoes of over 30t each were lowered to the bottom of the
pit within the jacket. Soil excavated by the backhoes was winched out of
the pit using a 1,500t barge-mounted crane with a 45 cubic meters clam-shell
device. Excavation was continued to a depth of approximately 40m below the
seabed, which is 75m below the island's surface. Kajima has considerable
experience in large-scale excavation for building underground tanks, circular
bases for bridge piers, and other structures, but the scale and difficulty
of the excavation work for the Kawasaki Man-Made Island was unprecedented.
In view of the huge water pressure on the unfinished island's exterior,
the Company established a thorough safety system--installing approximately
800 measurement instruments around the circumference and monitoring real-time
data provided by the instruments around the clock.
„When the excavation work was completed, prefabricated steel reinforced
concrete blocks 27m tall and weighing approximately 2,200t each were lowered
inside the island's circumference and more concrete was poured to create
an integral unit, including starting-holes for shield-driving machines as
well as the internal structure of the ventilation towers. |
|
|
The Undersea Tunnels
After completing the Kawasaki Man-Made Island, tunnel excavation was
begun. The Tokyo Wan Aqua-line is to be housed in two tunnels, one with
two eastbound lanes and one with two westbound lanes. The underwater portion
of the highway stretches 9.4km from Kawasaki to the Kisarazu Man-Made Island.
The tunnels for this portion were created using eight shield-driving machines.
Kajima is responsible for constructing the tunnel with eastbound lanes extending
1.8km from Kawasaki to the Kawasaki Man-Made Island, which is being carried
out during the period from July 1992 through December 1997.
Because of such factors as those related to the durability of machinery,
the maximum distance that can be tunneled with a single shield-driving machine
based on current technology is approximately 3km. Accordingly, to create
longer tunnels, shield-driving machines must tunnel from opposite directions
with considerable precision so that the machines can meet at a specified
position with less than 50mm deviation. In view of this stringent requirement,
a relative position monitoring system for shields, developed with the participation
of Kajima, was employed to ensure accurate meeting points for the shield-driving
machines that created each of the Tokyo Wan Aqua-line's four tunnels.
With regard to the tunnel that Kajima was responsible for creating, when
the two shield-driving machines were 50m from their meeting point, they
were slightly out of alignment with each other. As a result of adjustments
made over the remaining distance, the machines were ultimately less than
10mm out of alignment when they met.
After freezing the tunnel walls in the vicinity of the meeting point,
the shield-driving machines were partially disassembled and removed from
the tunnel, which was fundamentally complete at that time.
Aiming to complete the Tokyo Wan Aqua-line in December 1997, the lining
of the tunnels with concrete is currently proceeding. When the highway is
finished, following nine years of work, vehicles will be able to pass from
one side of Tokyo Bay to the other in less than 15 minutes. |